Project Portal · MA-2401

Pacific Heights Residence

Welcome back, Anna Whitman. Here's where things stand on your project, what's arriving next, and what's on the horizon.

Estimated Completion

May 30, 2025

Wrapping up

Project Lead

Eleanor Vance

Location

San Francisco, CA

Started

Jan 12, 2024

Overall Progress

82%

Current Phase

Installation

Next Up

Primary suite install

Scheduled May 2, 2025

In progress

Project Phases

Roadmap

  1. Discovery

    Site survey, brief, programming, initial budget.

    Complete

    Jan 12Mar 4

  2. Design

    Concept, schematic, design development, finishes.

    Complete

    Mar 5Jul 22

  3. Procurement

    Specification, ordering, vendor coordination, tracking.

    Complete

    Jul 23Dec 18

  4. Installation

    On-site install, styling, punch list, walkthroughs.

    In Progress

    Dec 19May 15

  5. Handover

    Final reveal, care guide, warranty package.

    Upcoming

    May 16May 30

Milestones

Key dates

  • Discovery sign-off

    Discovery

    Mar 4, 2024

    Complete

  • Concept presentation

    Design

    Apr 18, 2024

    Complete

  • Design development approval

    Design

    Jun 30, 2024

    Complete

  • Final finishes signed

    Design

    Jul 22, 2024

    Complete

  • All long-leads ordered

    Procurement

    Sep 10, 2024

    Complete

  • Custom millwork received

    Procurement

    Dec 12, 2024

    Complete

  • Living & dining install

    Installation

    Sofas, rugs, dining table, lighting.

    Mar 21, 2025

    Complete

  • Primary suite install

    Installation

    Bed, casegoods, drapery, art hang.

    May 2, 2025

    In Progress

  • Punch list & styling

    Installation

    May 15, 2025

    Scheduled

  • Final reveal & handover

    Handover

    May 30, 2025

    Scheduled

Deliveries

What's arriving

Walnut dining table — custom

D-018 · Atelier Rossi

Delivered

Scheduled Mar 14, 2025

Living room sectional

D-019 · Holloway Upholstery

Delivered

Scheduled Mar 19, 2025

Primary bedroom drapery

D-020 · Linden Workroom

In Transit

Scheduled Apr 24, 2025

Out for delivery — arriving Thursday.

Primary bed & nightstands

D-021 · Atelier Rossi

Scheduled

Scheduled Apr 29, 2025

Hand-knotted runner — hallway

D-022 · Marrakech Imports

Delayed

Scheduled May 8, 2025

Customs hold — revised ETA May 12.

Commissioned artwork (3)

D-023 · Studio Aalto

Scheduled

Scheduled May 12, 2025

Studio Updates

Latest from the team

  • Apr 18, 2025

    Eleanor Vance

    Drapery on track for Thursday

    Linden Workroom confirmed delivery this Thursday. We'll install Friday morning ahead of the bed arrival next week.

  • Apr 12, 2025

    Eleanor Vance

    Walkthrough recap

    Thank you for the walkthrough this morning. We've logged the bedroom textile sign-off and updated the install schedule.

  • Apr 3, 2025

    Marcus Reid

    Hallway runner update

    The runner has cleared production and shipped from Marrakech. We're tracking customs closely and will share an updated ETA by next week.

  • Mar 21, 2025

    Eleanor Vance

    Living & dining complete

    Living and dining install wrapped today — full styling photos coming once the lighting is dialed in.

Questions?

Reach out to Eleanor Vance anytime — we're here to keep your project moving.